Chapter 5: Load take over (LTO)


Load take over is used if the plant needs to do a planned transition from the mains to the genset.

It could, for example, be if the mains transformer needs to be serviced.


To initiate an LTO sequence we need to change a few settings in the controller


1. We need to select another plant mode.

2. We need to set up an Auto start/stop input on the mains controller.